工业设备安装质量管理与控制研究

工业设备安装质量管理与控制研究
摘要: 工业设备的安装质量对于工业企业来说就是生命线,它直接关系到工业企业使用工业设备的效率,进而还对工业设备操作的安全性有着直接的影响。目前工业设备朝着大型化、智能化、高精度、高转速的方向发展,这也就对工业设备安装的质量管理与控制提出了更高的要求。本文通过对工业设备安装中最为常见的两大问题,即基础安装与焊接进行简单论述,并通过实例进一步说明。
abstract: the installation quality industrial equipment is the industrial enterprise’s lifeline, and it is directly related to the efficiency of industrial equipment for industrial enterprises, and also has a direct influence on the safety of industrial equipment operation. in the current, industrial equipment develops towards the direction of large-scale, intelligent, high precision and high speed, so it has put forward higher requirements to the quality control and management of industrial equipment installation. this article briefly discussed two most common big problems in the installation of industrial equipment, namely the basic installation and welding made further explanation through examples.
关键词:工业设备安装;质量管理与控制
key words: industrial equipment installation;quality management and control
1 工业设备基础安装与焊接质量控制
1.1 基础安装质量控制 工业设备的基础安装一般来说可分为三个阶段,即前、中、后阶段,其中安装前期就是指预先对设备所在位置进行地基处理准备,而安装中期是在前期的基础上完成工业设备正式安装的阶段,在这个阶段必须保证工业设备的精度,以使其能够运转良好,安装后期则主要是对基础安装作一个总结性的检测,使整个工业设备基础安装符合设计要求与标准。
1.2 焊接质量控制 焊接施工的质量也对工业设备的安装有着直接的影响,因此在焊接过程中必须对其质量进行有效管理与控制。在焊接之前,必须做好一系列的前期准备工作,包括焊接环境、焊接材料与设备、加工拼装情况、坡口尺寸与形状等方面都要严格控制质量,而后根据垫板、错边、间隙等实际情况方可开展焊接作业。在实施焊接的过程中,必须确认以下项目,即后热、保温;选择焊丝或焊条直径;层间温度;清根;前层焊缝状态;电弧位置;焊缝设置;运条方法;焊接速度;电弧电压;焊接电源以及焊接顺序,实施焊接的施工人员必须严格按操作流程执行。在完成焊接后,则应以相关标准与设计要求对焊接质量进行检查,包括弧板处理、内部缺陷、表面尺寸及缺陷等。只有通过一系列严谨、仔细的检查,才能保证工业设备焊接质量的完好,从而使工业设备在安装